Skip to content
Research Article Open access CC BY 4.0

Monitoring and Evaluation of The Reliability of Distribution Network with Distributed Generation

Stella Nkiruka EMECHETA, Raymond Onyeka Nwajuonye, George Chibuzor OKONKWO

Journal of Engineering Research and Reports · pp. 29–42 · Published 30 Dec 2021

10.9734/jerr/2021/v21i1217510

Abstract

With the growing population of Ezenei 11KV feeder radiating from the Asaba mains Injection Substation and overstretched distribution network, monitoring and evaluation of the reliability and improvement of distribution network feeder is essential. Failure of some of the equipment at supply restoration is frequent due to weakness of some of the line conductors and long usage of the equipment. In this research work, simulation, analysis and evaluation of the reliability and improvement of Ezenei 11kV feeder was investigated. Load data used were collected from Benin Electricity Distribution Company (BEDC) Asaba between February and April 2018 and this was used to model the sixty – seven (67) buses on the network using Electrical Transient and Analysis Program (ETAP). Load flow analysis was carried out on the modelled network using Newton – Raphson (N-R) iteration method to determine the various bus power (active and reactive) and voltage magnitude using the base and distributed generation injected power. Reliability study was carried out on the network and result showed that the load point indices were increasing as distance of load point increased from feeder. The Seventeen load buses which was Okeke bus to Starcom bus forms the location A. and St. Rebecca bus to Chief Ofili bus forms location B. while Odogu bus to Old Deputy Govt. bus forms location, Iyabi bus to MTN III bus forms location D. Okeke and Jimok water which are the closest load buses to the feeder have an Average Interruption Rate (f/yr) and Annual Output Interruption Rate (hr/yr) of 8.9264f/yr, 417.1507hr/yr while Victor Odogu and Auditor General has an Average Interruption Rate (f/yr) and Annual Output Interruption Rate (hr/yr) of 8.9318f/yr, 417.2857hr/yr and 8.9264 f/yr, 417.1507hr/yr. It was also observed that Chief Osita, Anacho and Estate buses had the highest Average Interruption Rate (f/yr) and Annual Output Interruption Rate (hr/yr).

Reliability Improvement assessment and assessment monitoring and evaluation loss sensitivity factor system indices ETAP photovoltaic newton-raphson

Cited by 1

Article metrics

Real usage data collected on this platform.

0

Page views

0

PDF downloads

0

Outbound clicks

1

Citations

Views by country

Approximate, from request IP at view time — not citizenship or institution. Countries with fewer than 5 views are grouped as "Other".

No views recorded yet.

Traffic sources

Referring site, by host.

No traffic recorded yet.

Views and downloads exclude known bots/crawlers. Citations combines this platform's own DOI-resolved index with each external source's own reported total — see Cited by above for individually listed citing works. Last refreshed 0 seconds ago.