Development of a Scheffe’s Model to Predict the Duration of Project Tasks

K. M. Oba

Journal of Engineering Research and Reports · pp. 117–124 · Published 17 Jan 2024

10.9734/jerr/2024/v26i11067

Abstract

This study was aimed at applying Scheffe’s approach to determine task durations with a three-component design, to a second degree. The PERT approach was adopted to estimate the durations of three tasks for a small construction project. The study further applied Scheffe’s simplex theorem to develop a linear regression model to predict the task durations using the durations from the PERT approach. The model-predicted results were found to be very close to those estimated by the PERT approach. The model was tested with a two-tailed student t-test and was found adequate and fit with an R2 value of 0.9986. This proved that Scheffe’s approach can also be used to estimate or predict the durations of project tasks for projects with up to 3 tasks.

Model prediction PERT project task duration scheffe’s simplex

Cited by 0

No indexed citations yet.

Article metrics

Real usage data collected on this platform.

9

Page views

0

PDF downloads

0

Outbound clicks

0

Citations

Views over time

Views by country

Approximate, from request IP at view time — not citizenship or institution. Countries with fewer than 5 views are grouped as "Other".

Traffic sources

Referring site, by host.

Views and downloads exclude known bots/crawlers. Citations combines this platform's own DOI-resolved index with each external source's own reported total — see Cited by above for individually listed citing works. Last refreshed 0 seconds ago.